Will become emergency shelter
CIP '14 includes high school generator project

 

     Under the Amelia County Capital Improvements Plan (CIP) for FY '14, a larger capacity emergency electrical generator will be installed at Amelia County High School and the high school would then become the county's designated emergency shelter. Currently the elementary school is the designated emergency shelter but has no generator.
    On Jan. 23 the planning commission recommended the board of supervisors accept the revised 2013-'17 CIP. The supervisors use the CIP for budget planning but approve projects and funding one year at a time.
    The FY '14 CIP includes the replacement of the existing generator at the high school with one that will provide sufficient power to cover the main portion of the building, including that portion that will be used as an emergency shelter. The current high school generator will be moved to the elementary school.
    In his justification, Amelia Emergency Management Director Kent Emerson wrote, "Amelia County must be prepared to establish an emergency shelter in times of disaster. The school buildings are the closest suitable public buildings within the county. None of the existing buildings have adequate emergency power generation capabilities."
    Mr. Emerson estimated the cost of this new project to be $118,000.
    Another new CIP project for FY '14 is the hardware, software and related items necessary to establish a countywide GIS system that will incorporate 911, water, sewer, zoning and other mapping requirements under single system. The project would be phased in over two to three years and phase one is expected to cost $40,000. Community Development Director David Whitaker said the system will require the employment of an in-formation tech person.
    The school board wants $50,000 to install cameras and security doors in all schools and the school administration office building.
    The most expensive new project is the second phase of the Hindle building renovation. The FY '14 CIP includes the planning and engineering for the renovation of the historic school building now that the roof has been replaced. The planning and engineering is expected to cost $137,000.
    Already on the list for FY '14 was the upgrade to the Jackson building housing the Amelia Historical Library. The project will include sidewalk installation, a handicapped ramp and upgrade to the existing parking area for safer access to the building. The project is estimated to cost $83,000.
    Also already slated for FY '14 is the re-paving of the school bus garage parking lot and bus loop and is expected to cost $76,000.
    A new telephone system for the elementary school was also already scheduled for FY '14. The new system is deemed necessary be-cause the manufacturer no longer supports the current system. The cost is estimated at $52,000.
    Other projects were moved back from FY '13, including the paving of the parking lot at the War Memorial Building (parks and rec gym) at an estimated cost of $80,000. This part of the Amelia Streetscapes Improvements project was split from the FY '13 project.
    Another FY '13 project that has been moved back is the second phase of the Emergency Operations Center renovation to include a new 911 center moved from the sheriff's office. This project, estimated to cost $350,000, was requested by Mr. Emerson and Sheriff Ricky Walker. The county spent $150,000 in the first phase of the EOC renovation in FY '12 and a further $500,000 is estimated to complete the renovation of the building, now slated for FY '15.
    The first phase of an expansion of the industrial park was also pushed back from FY '13. This project will extend roads and utilities in the county-owned park to provide access to a 15-acre site that could be developed into five better-marketable lots. The cost is estimated at $568,845.
    The county estimates it will cost $50,000 to add signage to the industrial park entrance.
    Improvements to the Boepple building, estimated to cost $42,000, will improve the efficiency and meet absentee voting requirements.
    The CIP includes $12,500 to install a sprinkler system at the football/baseball field at the Joe Paulette Memorial Park. The school division has agree to pay half the cost.
    Parks and rec wants to install a Honeywell Instant Alert system. The department would tie into the school division's instant alert system with its own pass code and list to enable parks and rec to inform participants of cancellations and provide other information. The cost of the project is estimated at $10,000.
    The public works department estimates the cost of replacing the 1994 emergency power generator for the courthouse at $80,000. The 20 kw generator would be replaced with a 100 kw unit that will provide power for a greater portion of the courthouse. This project was moved forward from FY '16.
    In all, the CIP for FY '14 would cost $1,749,345.
    Several projects were rejected by the planning commission for inclusion in the FY '2013-17 CIP.
    The replacement of six desktop computers and the addition of five laptop computers and accessories requested by the James L. Hamner Public Library for a cost of $16,458 was rejected by the commissioners as not meeting the criteria for CIP funding.
    The library's request for $15,000 worth of e-books and other electronic contents also did not meet CIP criteria.
    The repair of structural damage to the middle and high school buildings due to age was expected to cost $50,000 but was also rejected as not meeting CIP requirements as was the repair to the elementary school foundation at $10,000. Both projects were classified as more suited to the schools' "operational and maintenance" budgets.
    A generator for the elementary school was dropped entirely from the CIP in favor of replacing the high school generator and installing the old generator at the elementary school.
    Three cars and four school buses requested by the schools were moved to the new Vehicle Purchase/ Replacement Plan. The replacement of the public works department's 2002 Ford Ranger pickup and a zero turn commercial lawnmower were also referred to the vehicle plan.


 

 

Back to news